From today's investor demo to a closed pilot with 5–10 Ghanaian businesses in May 2027. Maximus runs as a card-as-a-service programme: licensed partners issue the card and hold the money, and Maximus is the software and customer experience on top.
As of 12 November 2026.
Four workstreams over eleven months. Pick an owner to see their part.
Swipe sideways to see the full timeline.
Dates are planning estimates. Provider onboarding usually sets the real pace: if Gate B slips, everything after it moves by the same amount. Engineering keeps going against sandbox stand-ins while the partners are being chosen.
Each phase ends at a gate. Don't spend on the next phase until every line under its gate is true.
What moves the plan to Gate A.
Estimates, not quotes. Replace each line with the provider and lawyer quotes at Gate A.
| Item | When | USD |
|---|---|---|
| Provider onboarding and first three months' minimum fees | Phases 2–5 | 8,000 |
| Prefunded card balance (locked, not spent) | Phase 5 | 4,000 |
| Legal opinion, provider contract, customer terms | Phases 1–4 | 3,000 |
| Independent security test | Phase 4 | 2,000 |
| Domain, logo, trademark search | Phases 1–3 | 1,000 |
| Reserve | Any | 2,000 |
| Total | 20,000 |
The four things most likely to move the dates or the budget.
| Risk | What we do about it |
|---|---|
| Provider minimums exceed the budget | Ask for a pilot tier. Fall back to a referral or co-branded programme. Use the demo to raise the gap. |
| USDC route needs its own registration | Lawyer's opinion at Gate B. If blocked, launch the mobile-money card first and keep USDC in the sandbox. |
| Provider onboarding takes longer than planned | Run enquiries in parallel. Keep engineering moving against sandbox stand-ins. |
| Identity checks and wallet screening cost extra | Make it the first question in every quote; buying them separately can cost more than everything else combined. |